Project:

The project is to repair/replace concrete areas of the taxiway due to cracks and spalls, resulting from the extreme and heavy usage. The approximate scope included: 300m of Existing caulked joint repairs, 250m of New crack repairs, 28sqm of Partial-depth spall repair, 158sqm of Partial-depth spall at joints repair and 375sqm of Full-depth repairs. 

Duration: Oct 2023 - June 2024
Contract Value: $576,000
Location: Baghdad, Iraq

 

Scope of Works:

  • Test/Trial Patch or Section 

  • Cleaning of Cracks/Spalls/Joints 

  • Crack Repairs

    o  Sawing the concrete

    o  Cleaning the sawn crack and surrounding areas
    o  Sealing the crack

  • Spall Repair 
    o    Sawing and removing the concrete
    o    Preparation of sub-base
    o    Clean the sawn spalls areas
    o    Rebar reinforcement and installing dowels
    o    Placing of patch material
    o    Filling of joints
    o    Curing

  • Clear site of all debris and signage.

Armag Armory.png

Armag Armoury Project

TED171~1_edited.jpg

Tennis Court Resurfacing,

US Embassy, Baghdad

Fire Damage Repairs.png

Fire Damage Repairs

SOW for Office Floor Plan .jpg

Outdoor Lighting and Office Refurb

Sun Shade_HVAC.png

Sun-Shade and HVAC

20x40 Storage Shelter_Crop.jpg

Storage Shelter 20m x 40ft

Concrete_2.jpg

Concrete Pier

T-Walls.jpg

T-Wall Installation

Taji_Shade_Completed.jpg

Taji Shade Structures

Electric%20Gate_edited.jpg

Electric Gates

Batch Plant_BDSC.png

Concrete Batching Plant

Turf_2.png

Soccer Field Turf Replacement

bottom of page